Friday, March 28, 2014

Method Statement -Erection of Temporary Hoarding

1.            OBJECTIVE

To outline the sequence of activities, method and resources needed for the operation of erecting temporary hoarding.

2.            SCOPE

The work shall include all labour, material, equipment, safety requirement and services necessary for the execution erecting temporary hoarding.

3.            WORK SEQUENCE FLOW

                _to attach drawing_

4.            MATERIAL

                Material to be used is as follows:-

                4.1          50 x 50 x 1.6mm thick SHS M.S Posts

                4.2          50 x 25 x 1.2mm thick RHS M.S Nogging

                4.2          50 x 25 x 1.6mm thick SHS M.S Braces

                4.3          0.3mm thick metal decking

                4.4          Nail

                4.5          Cement

                4.6          Sand

                4.7          Water

5.            EQUIPMENTS & MACHINERIES REQUIRED

                Equipments and machineries to be used are as follows:-

5.1          Minimum: One (1) number of JCB Backhoe (if required)

                5.2          Minimum: One (1) set of hand excavating equipment

                5.3          Minimum: One (1) set of steel work equipment

                5.4          Minimum: One (1) set of water levelling

                5.5          Minimum: One (1) number of spirit level

6.            SITE PREPARATION WORK

                6.1          Setting out boundaries of ground in the proposed perimeter.

7.            METHOD OF WORK

7.1          Determine the location of the temporary hoarding will be established with confirmation from the surveyor.

7.2          After getting confirmation, using the given point and mark the main pole as per alignment shown in the drawings(Appendix A). Center to center of the main column is3000mm.

7.3          Preparation of the main pillars started by using handdigging to the depth 400mm.

7.4          Pole-sized 50X50X1.6mm thk SHS M.S constructed using equipment such as spirit level, water level, and tape measure. Two workers used to establish the main pillars.

7.5          Pillars need to ensure accurate position along the fenceline at 3.0m (panel width) intervals and make sure the baseare sitting on an even level surface.

7.6          Erect the remaining pillars along the line as noted previously until the hoarding line is complete.

7.7          50x25x1.2mm thk nogging need to install three (3) lines to support metal deck panels.

7.8          Metal deck panels will be installed with the framehoarding as per Appendix A (spacing 4” for every panels).

7.9          This work will be repeated until completion.

7.10        Entrance gate will be erected at remaining area (refer item no.3) with support at both side (left and right) using welded angles.

 8.            QUALITY ISSUES·         Boundaries demarcation required to ensure no double handling or trespassing to others people land.

·         View inspection required during the process of erection hoarding.

·         Regular inspection to be carried out by weekly basis to ensure the hoarding in good condition.

9.            SAFETY ISSUES

·         Safety helmets and safety footwear should always be worn.

·         All soft spots or holes shall be identified and barricade if necessary.

·         The site shall be kept clear of unnecessary obstruction.

·         First aid kit boxes will be provided at site office.

·         During raining, no erection hoarding activities are allowed to work.

10.          ENVIRONMENTAL ISSUES

·         All workers shall ensure that tools and machinery are in a good condition to avoid any oil leakage that could harm to environment.

·         Construction waste from construction area must be collected into centralized garbage bin and disposed at the designated area.Posted by ika erika at 12:17 PM Email This

1 comment:

ANAK KU ANAK ASUHAN PASTI

  Macam-macam hal berlaku dimalaysia ni tapi saya hanya berminat untuk ulas isu ni. Pendidikan awal kanak-kanak di Pusat Asuhan Tunas Isla...