Friday, March 28, 2014

Method Statement -Concrete Mix (Site Mix)

1.0          OBJECTIVETo carry out the site mix concrete work as per approved design mix for each particular grade.

2.0          SCOPE

This method covers for site mix concrete and trial mix for grade 20N, grade 25N and grade 30N by using mixer truck (dry mix).

3.0          REFERENCESConstruction Drawings

Project Specifications

Inspection Request Form

Approved design mix

4.0          RESPONSIBILITIES Site Manager

QA/QC Engineer

Site Supervisor

Lab Technician

5.0          WORKERSMachine Operator

General Worker

6.0          MATERIALSCement, Fine Aggregate & coarse Aggregate, Water

7.0          HANDLING AND STORAGE OF MATERIALSHandling: Transport of concrete using mixer truck and 20 tonne of mobile crane to location of concrete work.

Storage:  Fine aggregate and course aggregate shall be place nearest at batching area.

                 Cement shall be place in the store in dry condition and protected from weather

8.0          PLANT, MACHINERY AND EQUIPMENTConcrete Mixer Truck.

Batch boxes (800mm x 800mm x 500mm)

Water tank (5786 litre)

Nominated lab (Hermes Lab, for compression test)

Cube mould

Weighing scale

Slump equipment

Wheel barrow

9.0          PREPARATORY WORKS9.1          Before the site mixes commence, check will be carried out to ensure all the various control devices of the concrete mixer is functioning properly.

10.0     WORK METHODOLOGY

           

            10.1     Prior to commencement of the site mix, batch boxes should be fabricated, measuring 800mm x 800mm x 500mm to measure the proportion of coarse and fine aggregate, based on of 1 bag cement (50kg with loose weight 1436kg/m3), 0.035m3. Meanwhile, water shall be fill in full water tank 5786 litre complete with measuring gauge. Therefore, quantity water shall be control as per approved design mix proportion.

            10.2     The coarse and fine aggregate shall be passed all the testing such as sieve analysis, aggregate crushing value, flakiness and other as per specification before placed into the concrete mixer.

            10.3     Before carry out the site mix, a trial site mix approximately 1m3of mix concrete shall be batched based on approved design mix to required grade of concrete to check workability of mix and compressive strength. A set six (6) 150mm concrete test cubes, 3 for testing at 7 days and 3 for testing at 28 days will be made and tested to achieve as per required target mean strength. Summary of mix proportion for trial mix as per table 1 below:

Table 1Materials required per 0.05 cubic metre of trial mix

Concrete Grade

(N/mm2)

Mix Proportion

(Cement: Sand: Course Aggregate)

Weight

Volume (m3)

Volume (L)

Cement per m3 “all in” No. bags of 50kg each

Cement

Sand

Coarse

Cement

Sand

Coarse

Water

20

1

2.63

3.95

14.25

0.014

0.021

9.25

0.29

25

1

2.20

3.68

18.5

0.016

0.019

9.25

0.37

30

1

2.14

2.43

19.5

0.016

0.018

9.25

0.39

10.4        When trial mix are approved, site mix shall be agitated for approximately 6-8 minutes to produce a certain quantity of mixed concrete to required grade within the mix to proportion as per table 3.

Table 2

Materials required per cubic metre of mix concrete

Grade

Mix Proportion

Weight (kg)

Volume (L)

Cement per m3 “all in” No. bags of 50kg each

Cement

Sand

Coarse

Cement

Sand

Coarse

Water

20

1

2.63

3.95

285

748

1125

185

5.70

25

1

2.20

2.68

370

814

991

185

7.40

30

1

2.14

2.43

390

836

949

185

7.80

10.4       Preparatory Work

10.4.1   Obtain relevant approved construction drawings from Consultant.

10.4.2   Obtain material characteristics test result from supplier as references.

10.4.3   Prepare required material, machinery and tools for site mix.

10.4.4   Prepare proper material storage location and facilities.

10.4.5   Prepare fresh concrete test tools and mould for preparation of compression test specimens according to specifications.

10.5       Work Execution

10.5.1   All tools and materials shall be cleaned from debris and other materials, which will affect the quality of concrete produced.

10.5.2   Volume of all materials shall be measured by using backhoe bucket whereby 1 bucket of fine aggregate is equal to 0.153cu.m and coarse aggregate 0.157cu.m.

10.5.3   Transportation and handling tools and equipment shall not affect the quality of concrete during the process of delivery.

10.6       Quality Control

10.6.1   The slump test shall be conducted using a cone test at random or instructed by SE.

10.6.2   Slump shall be visually checked to ensure conformance to the specification. The result shall be documented in the inspection sheet.

Testing method

·                     Concrete shall be poured into the slump mould in three layers. Each layer shall be tamped with the tamping rod as per specification.

·                     Once the cone is filled to the top, the concrete shall be removed from the mould by raising the mould slowly and carefully in vertical direction.

·                     The concrete slump is the measured using measuring tape immediately by determining the difference between the height of the mould and that of the highest point of the specimen being tested.

·                     The slump measured shall be recorded to the nearest 5mm.

10.6.3   For the Compression Test, specimen shall be prepared according to the specification. The test specimen shall be cured as tested as below :

A standard practice, 6 nos of cubes would normally be prepared for per day production. 3 nos shall be tested at 7 days and the balance 3 nos shall be tested at 28 days.

Testing procedure

·               Clean internal surface of the mould thoroughly.

·               Place the mould on a smooth, horizontal and rigid metal plate and hold the mould firmly in place.

·               The mould shall be filled in 4 approximately equal layers.

·               Each layer shall be tamped with 25 strokes and distributed in a uniform manner over the cross-section of the layer. The 2nd and subsequent layers shall penetrate into the underlying layer.

·               Later, concrete shall be filled to finished level with a trowel.

10.6.4   Test result shall be documented in the Concrete Cube Result and shall be submitted to Consultant and client.

10.6.5   The Compressive Strength of the Concrete Cube shall achieve as per stated in the table below :

Concrete Grade

(N/mm2)

Minimum Compressive Strength of Concrete Cube

at 7 days

at 28 days

≤ 15

-

-

20

14

20

25

17

25

30

20

30

11    SAFETY AND ENVIRONMENTAL ISSUE

11.1Safety

11.1.1   All workers shall provide with PPE (Personal Protective Equipment) and shall be worn every time they are entering the site. Safety Supervisor shall ensure all the workers wear all the safety equipment provided.

11.1.2   Portland cement can cause burns on unprotected skin. Do not breathe the dust from the Portland cement or aloe it in your eyes. A respirator and safety glasses are recommended.

11.1.3   Safety Supervisor shall ensure that the activity shall ensure that activity shall carried out in a safe manner.

11.1.4   All workers shall fully support and actively participate in all safety related activities and comply with all practicable safety measures.

11.1.5   All workers shall be advised to report any accident or injury to supervisor and proper treatment to be obtained.

11.1.6   The safety supervisor shall ensure that workers understand the safety regulations and explain in detail in particular hazards, where the workers are working and the precaution to be taken to ensure their safety.

11.2Environmental

11.2.1   All workers shall ensure that all tools and equipment machinery are in good condition to avoid any oil leakage that could harm to environment.

11.2.2   Water from particular construction area shall be diverted into proper drain which is eventually empties into silt trap.

11.2.3   Domestic and construction waste from construction area must be collected into centralized garbage bin and disposed at the designated area.

No comments:

Post a Comment

ANAK KU ANAK ASUHAN PASTI

  Macam-macam hal berlaku dimalaysia ni tapi saya hanya berminat untuk ulas isu ni. Pendidikan awal kanak-kanak di Pusat Asuhan Tunas Isla...